With the Garden Grove Freeway (SR-22) Improvement Project more than halfway complete, the "New 22" is nearly here! Here is a snapshot of completed improvements, to date, to deliver a safer, faster and easier commute:
New bridge decks have been poured at Newhope Street and Taft Street in Garden Grove.
Construction to replace the eastbound SR-22 connector to the northbound I-5/SR-57 connector is underway.
25 out of 35 bridges are under construction.
There are 4 pile driving rigs working continuously throughout the project corridor.
35% of paving operations are complete.
75% of retaining walls are complete.
32% of soundwalls are complete.
For the most current project information, please visit our website at www.octa.net/sr22 or call Christina Byrne, OCTA Community Relations at (714) 560-5717.