As we reach the halfway mark in the 800-day construction process, heres a quick look at the tremendous progress thats been made in improving the SR-22:
Design is currently 90% complete.
Re-opened the first reconstructed off-ramp westbound
SR-22 at Haster St.
19 of 35 bridges are now under construction
New southbound SR-57/I-5 elevated connector to
westbound SR-22 is under construction
Concrete paving has begun.
Construction of retaining walls throughout the SR-22
Construction of the first soundwall is nearly complete.
To date, more than 745,000 hours of labor in
improving the New 22